Hanna Avenue Update


From: Phil Hunter, Hannah Avenue Project Supervisor....

To All:

See the [above] attached information update.

The tentative schedule is to remove the south half of the Hanna and Shelby intersection for asphalt replacement beginning at 6:00 p.m. on Friday, June 10, 2011. This area will be closed until approximately 11:59 p.m. on Sunday, June 12.

Please contact me if you have any questions.

Phillip Hunter

Project Supervisor

Bernardin, Lochmueller and Associates, Inc.

Field Office: (317) 786-9826